At 5 a.m. on June 14, in donghua technology general contracting of shanxi coal group yulin chemical coal points using the system of chemical new material demonstration project first phase project of 1.8 million tons/year ethylene glycol ethylene glycol plant project site, the six CO cycle gas turbine finished turn 18 hours of continuous rush job, charge drive laid a solid foundation for the project as planned.
Under the careful planning and preparation of the Project team of Donghua Science and Technology, the main steam S1 pipe network of the project started to warm the pipe at 9 o 'clock on June 13th. Then, 6 CO cycle steam turbines completed the continuous flushing and turning work for 18 hours. The turbine speed reaches the expected value, and all parameters meet the design requirements. The system runs stably.
At present, the purge, flushing, airtight and water combined transportation work of a series of devices in the project has been basically completed, and the catalyst loading will begin soon. Preparations for the second and third series of test runs are progressing steadily. The project team of Donghua Science and Technology united as one, to ensure the delivery of high-quality construction results for the owners, as soon as possible to achieve the project start-up target.